Public Utilities Projects

Engineering

1700 EAST STORM DRAIN REHABILITATION:

We have received all project closeout documents and we are processing final payment to the contractor. If you have any questions or would like more information regarding this project, please contact Tyler Shelley at 801-568-7285.

LOST WOOD STORM WATER REPLACEMENT PROJECT:

We are replacing the Corrugated Metal Pipe (CMP) in Lostwood Drive. The CMP pipe has been corroded by the salt applied on the road. We are designing this project in house and with the help of the Public Works department. We are planning to replace the entire stretch of asphalt from Wasatch to Dimple Dell. We are in the final stage of the design to install Reinforced Concrete Pipe (RCP) in Lost Wood Drive. We have produced 95% drawings for staff to review. We plan to advertise in the newspaper the first two weeks in May and have the bid opening in mid May. If you have any questions, please contact Tyler Shelley at 801-568-7285.

700 EAST AND 1300 EAST WATERLINE PROJECT:

We received two bids from pre-qualified contractors. The lowest bid came in above our budget for both project areas. We have decided to award Cliff Johnson Excavating Schedule A and Schedule B (700 East Waterline Project) and rebid Schedule D (1300 East Waterline Project) in June 2016. The contract has been signed and the Notice to Proceed has been issued. We held the pre-construction meeting on April 26, 2016. The contractor plans to mobilize the site on May 2, 2016. If you would like more information on these projects please contact Lennie Chanthaphuang at 801-568-7293.

WELL AND PUMP STATION MAINTENANCE SERVICES (2016 WILDFLOWER WELL REHABILITATION):

Nickerson Company has pulled the pump and taken it back to their shop for inspection. Because of the intensive repairs that would be required, Nickerson has recommended replacing the pump. We have concurred with their recommendation. They are scheduled to install the new pump on April 25th. If any questions on this, please contact Richard Benham at 801-568-6074.

FLAT IRON TANK REPLACEMENT PROJECT:

Our selection committee met on March 23, 2016 with the purpose of choosing engineering firms to be invited to submit proposals for engineering services for the above referenced project. During the meeting we ranked each of the SOQ's that the department has on file. We have selected Bowen Collins and Associates, Hansen Allen & Luce, Forsgren Associates, Jones & DeMille, and Stantec to submit proposals. We have met with each of the five consultants that we have invited to submit proposals to answer questions. We sent the consultants a revised Request for Proposals that clarified a few items from our meetings with each of the consultants. The proposals will be due on May 4, 2016. If you would like more information, please contact Richard Benham at 801-568-6074.

2015 STREETLIGHT INSTALLATION PROJECT:

The contractor has restored, installed, and replaced sidewalk, asphalt, and landscaping on Viscounti Drive and Viscounti Circle. We have produced a punch list of items that need be completed for Copper Creek Road, Cottage Avenue, and Harrison Drive. The next street that we will do a walk through inspection and produce punch list items will be Lone Peak Park Drive. If you have any questions, please contact Lennie Chanthaphuang at 801-568-7293. 

MONROE STREET/10000 SOUTH STORM DRAIN IMPROVEMENTS:

The storm drain has been installed in 10000 South up to the east side of the I-15 overpass. We are coordinating with UDOT to clean out the detention pond just west of the freeway to allow the pond to drain better and keep water from backing into the new storm drain. If you would like more information on this project, please contact Tyler Shelley at 801-568-7285.

SANDY CANAL ENCLOSURE PROJECT:

Draper Parkway Detention and Piping -- All project closeout documents have been received from the contractor and we are processing the final payment.

9400 South to 9800 South -- We met with Salt Lake County Flood Control and Parks and Recreation Departments to discuss alternatives for the project. The preferred alternative at this point is a shallow large detention basin in Bear Park. We will continue coordinating with the County and doing further design and analysis to evaluate this alternative. If you would like more information regarding this project, please contact Tyler Shelley at 801-568-7285.

Operations Update

April_2016.pdf
Data Format: pdf
File Size: 110 KB