Public Utilities Projects

Engineering

DRY CREEK HYDROLOGY STUDY:

We held a scoping meeting with Bowen Collins & Associates and processed the Notice to Proceed for this project. We then held a kick-off meeting with them, Salt Lake County Engineering, Public Works, and representatives from administration to coordinate the three different projects that are all affected by the resultant study. BCA is quickly performing the preliminary hydraulic and hydrologic analysis to get some numbers that we can work with, and then they will finalize the report/study. If you would like more information regarding this project, please contact Richard Benham at 801-568-6074.

SANDY PARKWAY WATERLINE PROJECT:

The contract is ready to be signed by the contractor. Once the contract has been signed, we will produce the Notice to Proceed. We have scheduled a preconstruction meeting on July 23, 2014 and construction will begin. If you would like more information regarding this project, please contact Lennie Chanthaphuang at 801-568-7293.

MONROE STREET/10000 SOUTH STORM DRAIN IMPROVEMENTS:

Bowen Collins & Associates has provided us with a proposal to develop a design to improve the storm drain system in the Monroe Street/10000 South area. These improvements are in accordance with the recommendations in a memo concerning the impacts of the Central Business District Development on the storm water system. We held a meeting with our consultant to discuss the progress of the design. We still need to do some verifications and camera work on existing pipe. We are hoping to reduce the overall pipe size of the storm drain line. If you would like more information on this project, please contact Lennie Chanthaphuang at 801-568-7293.

RICHARDS DITCH WELL REHABILITATION PROJECT 2014:

Widdison Turbine ran a video inspection inside the well on Friday, June 6th to verify the exact depths of the well that need to be perforated. The contractor has also started the process of perforating selected screens. If you would like more detailed information on this project, please contact Lennie Chanthaphuang at 801-568-7293. 

9400 SOUTH WATER LINE I-15 CROSSING PROJECT:

This project is nearly complete. The only items remaining are to complete the testing on the 20" HDPE line that goes under I-15 and the 12" line that runs down 9120 South and to install a few more valve collars in the parking lot at 9400 South on the east side of I-15. If you would like more information regarding this project, please contact Richard Benham at 801-568-6074.

SANDY CANAL ENCLOSURE PROJECT:

We met with Draper City on multiple occasions and have worked out a conceptual agreement with them to connect storm water runoff from the Eastridge Detention Basin into their detention basin just north of 12300 South. In exchange for allowing this, we have offered to pay for construction improvements to the pond. We will help fill in the canal portion from that location northward within Draper City's boundary. Further to the north, we have received and reviewed the construction plans and specifications prepared by our consultant. Once the agreement is finalized with Draper City we can advertise and bid this next section for construction. We have a contractor providing and placing fill material in the section between 11400 South and Sunburn Lane. They have about half of the work completed in this section. We are finalizing the agreement and setting a schedule for the section of canal in the vicinity of 700 East near Savannah Drive. We will be crossing the private property with a new pipe line to drain this area. If you would like more information regarding this project, please contact Rod Sorensen at 801-568-7297.

PEPPERWOOD TANK REPLACEMENT:

The contractor is continuing to work on the concrete retaining wall and finish work inside the vault. Once the retaining wall is finished then the backfill will be completed. The project is on schedule to be completed the end of August. If you have any questions, please contact Richard Benham at 801-568-6074.

WINDY PEAK STORM WATER PROJECT:

The contractor has backfilled the west portion of the box culvert work in 1000 East. This next week the contractor will move traffic to the west side of 1000 East and work to finish the box culvert. The contractor also has a crew working to finish up on Windy Peak Drive. The contractor will be paving Windy Peak this week. If you have any questions on this project, please contact Richard Benham at 801-568-6074.

Operations Update

April_and_May_2014.pdf
Data Format: pdf
File Size: 438 KB