Public Utilities Projects

Engineering

7800 SOUTH WATER SERVICES PROJECT:

We received a bid from KK&L Administration to replace three galvanized services using directional drilling on 7800 South at 560 East, 570 East, and 574 East. The contract is being routed for signatures. Once the contract is signed, we will produce the Notice to Proceed and have a preconstruction meeting and construction will begin. If you have any questions, please contact Lennie Chanthaphuang at 801-568-7293. 

DRY CREEK HYDROLOGY STUDY:

We held a scoping meeting with Bowen Collins & Associates and processed the Notice to Proceed for this project. We then held a kick-off meeting with them, Salt Lake County Engineering, Public Works, and representatives from administration to coordinate the three different projects that are all affected by the resultant study. BCA is quickly performing the preliminary hydraulic and hydrologic analysis to get some numbers that we can work with, and then they will finalize the report/study. If you would like more information regarding this project, please contact Richard Benham at 801-568-6074.

SANDY PARKWAY WATERLINE PROJECT:

The contractor, Newman Construction has installed new 10-inch PVC C900 pipe on Sandy Parkway from 9000 South to approximately 8650 South. They are in the process of doing the water services and connections. Once those items have been installed, they are planning to asphalt the road and start a new trench going northward. If you would like more information regarding this project, please contact Lennie Chanthaphuang at 801-568-7293.

MONROE STREET/10000 SOUTH STORM DRAIN IMPROVEMENTS:

Bowen Collins & Associates has provided us with a proposal to develop a design to improve the storm drain system in the Monroe Street/10000 South area. These improvements are in accordance with the recommendations in a memo concerning the impacts of the Central Business District Development on the storm water system. We held a meeting with our consultant to discuss the progress of the design. We still need to do some verifications and camera work on existing pipe. We are hoping to reduce the overall pipe size of the storm drain line. If you would like more information on this project, please contact Lennie Chanthaphuang at 801-568-7293.

RICHARDS DITCH WELL REHABILITATION PROJECT 2014:

We had a meeting with Kyle Widdison, owner/manager of Widdison Turbine to go over the project. Because of the complication and the uniqueness of this project, we have extended the contract time from June 30, 2014 to November 14, 2014. The contractor has removed all of the equipment from the site and will be bringing in a 120 ton crane in an attempt to pull the casing. If the casing can successfully be pulled, they will start the new gravel pack. If you would like more detailed information on this project, please contact Lennie Chanthaphuang at 801-568-7293. 

9000 SOUTH to 9400 SOUTH WATER LINE I-15 CROSSING PROJECT:

We walked the site with the contractor and produced a punch list of items for final completion on July 30, 2014. The contractor has 30 days to complete the punch list items. We anticipate that all work including the punch list items will be finished in the next couple of weeks. Once we receive a final payment request and final documents, we will close out the project. If you would like more information regarding this project, please contact Richard Benham at 801-568-6074.

SANDY CANAL ENCLOSURE PROJECT:

The Riparian to Sunburn Lane Storm Drain Project phase of Sandy Canal was awarded to Lyndon Jones Construction. Alternatives are being analyzed for the storm drain flows from Savannah Drive. We are coordinating with White City and Salt Lake County for the 9400 South to 9800 South portion. We are looking at some alternatives for this portion of the project as well. If you would like more information regarding this project, please contact Rod Sorensen at 801-568-7297.

PEPPERWOOD TANK REPLACEMENT:

Landscape rocks, topsoil, and sprinkler system at the tank site are being installed. The road base material needed for the parking area and roadway has been placed and asphalt is expected next week (Sept 16th). The contractor recently performed a hot-tap for the connection of the 10-inch pipeline. If you have any questions, please contact Richard Benham at 801-568-6074.

WINDY PEAK STORM WATER PROJECT:

The project is nearly complete. With the exception of a few remaining items, the contractor is in the process of completing concrete collars, videoing the storm drain pipe, and final cleanup. A final walk through is scheduled and a punch list of all remaining items will be made. Once final quantities have been reconciled and punch list items have been completed, the project will be closed out. If you have any questions on this project, please contact Richard Benham at 801-568-6074.

Operations Update

Operations_Update_August_2014.pdf
Data Format: pdf
File Size: 235 KB