Public Utilities Projects

Engineering

LONE PEAK EXPLORATORY WELL PROJECT:

We have received proposals from three engineering firms which were distributed to and reviewed by selection committee members. The members of the committee met and evaluated the proposals together. Loughlin Water Associates, LLC was selected for the project. The contract has been finalized and we met with the consultant to coordinate and begin work on the project. If you have any questions regarding this project, please contact Tyler Shelley at 801-568-7285.

PALMER WELL REHABILITATION

The new pump has arrived and the contractor will be on site this week to install the pump and finish the project ~ February 23, 2015. If you have any questions, please contact Richard Benham at 801-568-6074.

2015 STREETLIGHT INSTALLATION PROJECT:

The Public Utilities department has received three proposals from engineering firms to assist us with the design and construction management of the 2015 Streetlight Project. We held a kickoff meeting on Wednesday, January 7, 2015. Wright Engineering, the consultant that was selected, will be submitting a 50% drawing during the week of February 23rd. If you have any questions, please contact Lennie Chanthaphuang at 801-568-7293. 

DRY CREEK HYDROLOGY STUDY:

We held a scoping meeting with Bowen Collins & Associates and processed the Notice to Proceed for this project. We then held a kick-off meeting with them, Salt Lake County Engineering, Public Works, and representatives from administration to coordinate the three different projects that are all affected by the resultant study. BCA is quickly performing the preliminary hydraulic and hydrologic analysis to get some numbers that we can work with, and then they will finalize the report/study. If you would like more information regarding this project, please contact Richard Benham at 801-568-6074.

MONROE STREET/10000 SOUTH STORM DRAIN IMPROVEMENTS:

We met with Bowen, Collins and Associates to discuss design of the storm drain. We are scheduled to meet with Public Works to coordinate construction of the storm drain and the Monroe Street widening and reconstruction project. Bowen, Collins and Associates will be beginning design on the project once survey and property information from Public Works is provided to them. If you would like more information on this project, please contact Lennie Chanthaphuang at 801-568-7293.

RICHARDS DITCH WELL REHABILITATION PROJECT 2014:

The contractor has finished trimming, cleaning, and preparing the screens for installation. The new sections of screen have arrived. The contractor has also been perforating the old outer casing. They are planning to start rehabilitating the well in the next couple of weeks. If you would like more detailed information on this project, please contact Lennie Chanthaphuang at 801-568-7293. 

SANDY CANAL ENCLOSURE PROJECT:

The Riparian to Sunburn Storm Drain Project of the Sandy Canal fill-in has been completed, with the exception of some minor cleanup items. We have received the video inspection from the contractor of the installed storm drain. We have received almost all of the project closeout documents from the contractor and are processing a change order to balance installed quantities. If you would like more information regarding this project, please contact Rod Sorensen at 801-568-7297.

PEPPERWOOD TANK REPLACEMENT:

We met with the contractor, Gerber Construction on site to review the minor repairs on the inside of the tank. The brackets have been replaced and the contractor is planning on making the other repairs in the next few weeks. If you have any questions, please contact Richard Benham at 801-568-6074.

Operations Update

Nov_and_Dec_2014.pdf
Data Format: pdf
File Size: 281 KB