Public Utilities Projects

Print
Press Enter to show all options, press Tab go to next option

Engineering Projects

FLAT IRON TANK REPLACEMENT:

The city has constructed a new 5 million gallon tank that is structurally sound and provides more water efficiently to the city. This phase of the Public Utilities work in the park is nearing completion. 

September 16, 2019 update:  The contractor continues to install irrigation system on the north side of the tank. The fence around the tank overflow has been completed. They are planning to hydro-seed the site late September.

For more information, please contact Richard Benham at 801-568-6074 or Lennie Chanthaphuang at 801-568-7293.

FLAT IRON WELL DRILLING:

The purpose of this project is to construct a new drinking water well on the southeast side of the new 5 million gallon tank in Flat Iron Mesa Park.  The new well will replace an old well located north of the park that had to be abandoned.  After completion of the well drilling, a well house will be constructed around the well.

Click here for project flyer: Flat Iron Well Project Flyer

August 23, 2019 update:  The project is completed.  The contractor has cleaned up the site and has demobilized. We are waiting for final documentation before we close out this project.

For more information, please contact Richard Benham at 801-568-6074 or Lennie Chanthaphuang at 801-568-7293.

DRY CREEK IMPROVEMENTS PHASE 2:

Sandy City completed a Concept Plan for Dry Creek in 2018. The purpose of the Dry Creek Improvements project is to complete critical infrastructure improvements along the Dry Creek corridor to 1) eliminate flooding potential in the Sandy Cairns downtown area, 2) restore the channel and convert it from an overgrown hazard to a central feature of the Sandy Cairns downtown area with recreational features including open space, trails, and the Art Walk, and 3) provide demonstrations for public education along the corridor of Low Impact Development (LID), water conservation, and water quality Best Management Practices (BMPs).

Phase 1 (between Monroe Street and I-15) of the Dry Creek Improvements Project was completed in 2016. Phase 2 (between Monroe Street and Centennial Parkway) consists of 400 linear feet of channel restoration that includes grading, riprap, landscape and irrigation, a 60 linear foot prefabricated pedestrian bridge, concrete trail, lighting, small shade structures, picnic tables, benches, trash cans and pedestrian ADA ramps.

July 31, 2019 update:  The grass has been installed on the project.  We will be working with the engineer and contractor to cleanup and finalize the project. We will soon have a final walkthrough.

If you would like more information, please contact Tyler Shelley at 801-568-7285.

DRY CREEK IMPROVEMENTS AT 10200 SOUTH:

Sandy City storm water operations personnel had the project site blue-staked and are now performing underground utility investigation work to identify the location and depth of utilities that may be in conflict with the proposed flood control facilities.  We met with Hansen, Allen & Luce (HAL) to review the design and discuss schedule. We had a 60% design review meeting last week and reviewed the drawings and discussed permit applications and other construction related details. We are contacting utility companies to discuss the potential utility conflicts on the project.  We will be coordinating with them to identify potential relocation of utilities that may need to be performed. Qualified bidders were contacted last week to inform them of the pre-qualification and schedule for bidding and construction.

If you would like more information, please contact Tyler Shelley at 801-568-7285.

2018 STREETLIGHT PROJECT:

The purpose of this project is to install 19 residential streetlights throughout the City.  These new lights were planned in accordance with our Streetlight Master Plan.

June 7, 2019 update:  the contractor has finished installing all the streetlights. All streetlights are lit and are functioning. The contractor has come back to restore the asphalt, concrete, and landscape. Once they complete the work, we will walk the site and produce punch list items.

If you would like more information, please contact Lennie Chanthaphuang at 801-568-7293.

SANDY CANAL TRAIL - 10600 SOUTH TO DIMPLE DELL:

We have been working over the last several years to complete necessary storm drain projects and convert the Sandy Canal corridor into a trail system. The trail has been completed from the south end of the Sandy City, up to 10600 South. Salt Lake County has completed design for and will bid out this summer, a project that includes a bridge across Dimple Dell and trail improvements from Carnation Drive to Bear Park. We are collaborating with White City Metro Township on a project to complete trail and drainage improvements along the Sandy Canal corridor from 10600 South to Dimple Dell. This project will connect the completed trail at 10600 South to the County project at Carnation Drive.

August 29, 2019 update:  The contractor has started clearing, grubbing and removing the concrete in the channel. We met with the contractor on site to identify the trees that will need to be trimmed and removed. We have continued to receive and review submittals from the contractor for the materials and products that will be used on the project.

If you would like more information, please contact Tyler Shelley at 801-568-7285. 

2018 WATERLINE  PROJECTS: 10600 SOUTH, RIVER OAKS AND 7800 SOUTH:

This project includes waterlines in the River Oaks Subdivision, 10600 South at State Street and a short section of 7800 South (450 East to 550 East).  Because of the busy construction climate, we will allow the contractor to complete these sections anytime during the construction season providing that once the contractor begins a section they must complete that section in a timely manner. We are hopeful that this approach will also result in lower bids.

August 29, 2019 update: The contractor has substantially completed all three areas of the project: 7800 South, 10600 South and River Oaks. Regarding the 10600 South State project, the contractor will be removing abandoned water valves in State Street and 10600 South next week. 

For more information regarding this project, please contact Mason Clark at 801-568-7297 or Lennie Chanthaphuang at 801-568-7293.

HARRISON STREET WATERLINE AND STORM DRAIN:

There are currently three waterlines that cross I-15 and supply water to the portion of the City west of I-15. The waterline in 9000 South is badly corroded and has had several costly breaks in the last few years. Replacing 9000 South water line with a new crossing north of 9000 South was added to our capital projects list in 2015. The proposed new supply line across I-15 is planned to be installed at approximately 8550 South. In addition to the new supply line, the existing waterline in Harrison Street needs to be replaced and up sized. As part of the proposed project, the existing 6-inch diameter waterline in Harrison Street will be replaced with an 8-inch diameter waterline from approximately 8800 South to Cottage Avenue and with a 12-inch diameter waterline from Cottage Lane to approximately 8550 South. (Phase 1 - Waterline Improvements). 

The new storm drain improvements west of Monroe Street will convey the storm drain runoff flows and irrigation tailwater north along Cottage Avenue and Harrison Street to the 60-inch diameter storm drain outfall in 8600 S.  The completion of this project will eliminate the storm drains on private property, reduce maintenance, and increase storm drain capacity in the area.

August 29, 2019 update:  The storm drain line on Cottage Avenue and Monroe Street are finished. The asphalt sub-contractor is currently on site prepping for payment on Monroe and Cottage Avenue. The prep should be finishing up and the paving will take place after the holiday. The contractor is continuing water service connection in Harrison Street.

If you would like more information, please contact Tyler Shelley at 801-568-7285 or Mason Clark at 801-568-7297.

10600 SOUTH WATERLINE PROJECT (ZONE 5 TRANSMISSION LINE):

August 29, 2019 update:  We are installing a 20-inch waterline on 10600 South from 700 East to 1300 East. The contractor continues to install the 20-inch water pipeline. They are approximately 40% finished with the waterline installation.

For more information regarding this project, please contact Lennie Chanthaphuang at 801-568-7293.

 Operations Update

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer